Cement, Sand And Granite (concrete) Mix Explained






Good Day:
Lets explain concrete mix and how your bricklayer is expected to mix your next foundation / decking.

Most time as Non-Construction experienced house builders, we put our trust on the bricklayers to mix our concrete rightly, however very few of them can be trusted to do the right thing - If your bricklayer negotiated for material and labour (its even more difficult to trust him) because he might be maximizing gain and reducing materials; often times even when you buy your materials; they tend to put in excess sand, granite ratio to minimize time spent in doing the job.

LETS DISCUSS THE BASIC RATIOS AND WHAT IS EXPECTED OF THEM.

We'll start by explaining what the ratio 1:2:4, 1:3:6 etc. means - What this means is the Cement, Fine aggregate and Coarse aggregate ratio. Where fine aggregate could be Sharp Sand or Stone dust and Coarse aggregate could be granite, gravel or stone-base (for certain project types).

1:2:4 therefore means, 1 part of cement : 2 part of fine aggregate : 4 part of coarse aggregate. This 'part' as used refers to volume. It means If I have 1 head-pan of cement, I'll need 2 head-pan of sharp sand and 4 head-pans of granite / gravel or 1 cup of cement, 2 cups and 4 cups respectively of sand and stone.






The above is the theory of the mixture.... but practically on site; their might be need to modify a bit.

Comparing Granite and Gravel:

Granite are basically rocks blasted and keep 'neat' while gravel are rocks that come with a lot of 'dirt' i.e sand. (in my terms) - It means if I have 2 head-pans of granite; I have 2 head-pans of granite but in the case of gravel, if I have 2 head-pans of gravel, what I have is probably 1 head-pan of gravel + 1 head-pan of gravel sand.


The implication is simply:

If I'm working with granite, I can maintain my mix ratios as theory has it but when working with gravel, you are expected to reduce the quantities of sand in it (because gravel itself contains too many sand) so you don't end having too much sand hence the theoretical ratios can't work.

Solution:
The solution to this is by mixing the first bag of cement & aggregate on site and adjusting the quantities accordingly.

Relationship Between Concrete Elements:

CEMENT - SAND - STONE relationship; In practice a 50kg of cement bag contains 2 head pan of cement; this means that if i have a plan to mix 1 bag of cement my mixing ratio would be:

1:2:4 = 1 bag of cement : 4 head-pans of sand : 8 head-pans of stone
1:3:6 = 1 bag of cement : 6 head-pans of sand : 12 head-pans of stone

but must you measure sand and stone in head-pans when you have large quantities to mix?

We have come to conclude also that 4 head-pans = 1 wheel barrow; so for my 1:2:4 mix - I'll have it as 1 bag of cement : 1 wheel barrow of sand : 2 wheel barrow of stone etc.

Over time on site however; you always find the above mix to have too much sand or too much stone....but that doesn't mean the ratios are wrong; IT MEANS OUR MEASUREMENTS ARE NOT ACCURATE - We can only get an accurate mix if we're using a batching plant (off-course not on our little project is this possible)


MY SOLUTION:
I've studied a ratio that works: and that's what I've always recommended on small projects, especially when the Manual Mixers (that mixes half bag at a time) are used.

1:3:3 is that mix.

HALF BAG OF CEMENT : 3 HEAD-PANS OF SAND : 3 HEAD-PANS OF GRANITE and if you're using gravel, you might need to reduce the sand content and increase the stone content to say 1:2:4 etc. mixed with about 30-35 ltrs of water.

Lastly; the other factor that affect this ratio is the size of stone; the smaller the granite size, the more you might need to add eg if I'm using the smallest chippings (1/4) of an Inch; I might need to make my ratio 1:3:4 instead of 1:3:3 to ensure adequate strength.

Lets create a 'healthy discussion' towards ensuring a safe construction practices...

Thanks.

Comments

Popular posts from this blog

How To Practically Calculate The Quantity (m2) Of Roofing Sheet Required

I've been wanting to do this topic but couldn't come up with the easiest way to teach it; while it is possible to measure the quantities of roofing sheets needed for your project even before you set the first block using the Architectural drawings; it requires a lot of experience especially in trigonometry and site visualization. I have however found an easy way around it; as would be discussed below. I have carefully designed and attached a roof plan for this purpose, (feel free to use should it fit your building design... lol) Calculating the quantity of roofing sheet needed is done is meter square (m2), same parameters used for selling and purchasing roofing sheets hence we would expect to use the AREA FORMULAS (i.e Area formulas for Rectangle / Square, Triangle, Trapezium and Rhombus), sounds easy right? Yes it is!!! The most difficult aspect of calculating Area of Roofing is FINDING THE TRUE LENGTH (Technical Drawing students should understand this)

How To Calculate Quantity & Cost of Asbestors or PVC Ceiling Needed 4 your project

Good-Day, I'll be taking us on calculating the quantity and approximate cost of Asbestos ceiling sheet and PVC ceiling for a mini-flat (I have attached a plan for this purpose) and as usual our measurement would be done using the standard millimeter (mm) mode of measuring. Note: If you're not familiar with the millimeters / meters tape, then find time to learn it or request for a tutorial in the comment box.

TIPS ON CHOOSING A PROFESSIONAL LAND SURVEYOR IN NIGERIA.

A Professional Land Surveyor renders a highly technical service in compliance with applicable laws, regulations, codes and court decisions set forth by the Surveyors Council of Nigeria (SURCON). Because of the special skills and complexities involved in surveying land, the government of Nigeria via its various agencies limits the practice to only those surveyors duly registered by the Surveyors Council of Nigeria (SURCON). In order to protect the public from inferior land surveying, there are Minimum Standards for all types of Land Surveys. These standards describe recommended procedures for a survey and the minimum information to be provided to the client. In choosing a Land Surveyor please follow these TIPS! Consider the qualifications of a Professional Land Surveyor. He is supposed to display his Registration Certificate in his office, please look out for it. Ensure that the Surveyor will be capable of meeting the requirements of the proposed survey. In selecting a prof